Chapter9 Reducing Project Duration 325 3. Use the information contained below to compress one time unit per move using the For each move identify what activity (ies) was crashed and the adjusted total cost Maximum Crash Time least cost method. Reduce the schedule until you reach the crash point of the network Normal Time Normal Cost 150 100 Act. Crash Cost (Slope) 100 200 150 Project duration 16 Total direct cost 1,400 Show transcribed image text
Expert Answer
Attached